The 90-day Fast-Track plan, week by week
- Weeks 1–2: site selection finalised, trade license + DED approval, DHA Initial Approval submission with pre-approved layout template.
- Weeks 3–6: fit-out construction (MEP, medical gases, signage), equipment procurement from partner stock, EMR setup, staff licensing in parallel.
- Weeks 7–10: equipment install + commissioning, pre-inspection mock audit, corrective actions, staff onboarding and SOPs.
- Weeks 11–12: DHA Final Inspection, license issuance, insurance empanelment fast-track, soft launch.